Excav by machine Excav trench to receive kerb
found ave size
450 mm * 150 mm |
m |
0.80 |
|
600 mm * 200 mm |
m |
1.00 |
|
300 mm * 100 mm
|
m |
0.60 |
|
Excav curved trench to receive kerb found ave size
450 mm * 150 mm |
m |
1.00 |
|
600 mm * 200 mm |
m |
1.50 |
|
Excav by hand Excav trench to receive kerb found
ave size
150 mm * 50 mm |
m |
0.10 |
|
200 mm * 75 mm |
m |
0.50 |
|
250 mm * 100 mm |
m |
0.75 |
|
300 mm * 100 mm
|
m |
1.00 |
|
Excav curved trench to receive
kerb found ave size
150 mm * 50 mm |
m |
0.25 |
|
200 mm * 75 mm |
m |
0.50 |
|
250 mm * 100 mm |
m |
1.00 |
|
300 mm * 100 mm
|
m |
1.00 |
|
PIain in-situ
ready mixed conc C7.5 - 40 mm aggregate poured on or against earth or
unbIinded core Found |
m3 |
75.00 |
|
BIinding beds thknss n e 150 mm |
m3 |
90.00 |
|
PIain in situ ready mixed designated conc C10 - 40
mm aggregate poured on or against earth or
unbIinded core Found |
m3 |
75.00 |
|
BIinding beds thknss n e 150 mm |
m3 |
85.00 |
|
PIain in situ ready mixed designated conc C20 - 20
mm aggregate poured on or against earth or
unbIinded core Found |
m3 |
75.00 |
|
BIinding beds thknss n e 150 mm |
m3 |
86.00 |
|
Precast conc kerbs, channeIs, edgings bedded,
jointed & pointed in cement mortar 1:3 incIuding haunching up 1 side
with in situ ready mix designated conc C10 - 40 mm aggregate to conc
base Edgings straight square edge
50 mm * 150 mm |
m |
6.00 |
|
50 mm * 200 mm |
m |
6.00 |
|
50 mm * 255 mm |
m |
7.00 |
|
Accessories
Precast conc, kerbs, channeIs
edgings bedded, jointed & pointed in cement mortar 1:3 incIuding
haunching up 1 side with in situ ready mix designated conc C10 - 40 mm
aggregate to conc base - straight Kerbs
125 mm * 255 mm |
m |
9.00 |
|
150 mm * 305 mm |
m |
11.00 |
|
curved Kerbs
125 mm * 255 mm |
m |
13.00 |
|
150 mm * 305 mm |
m |
18.00 |
|
ChanneIs
255 * 125 mm straight |
m |
9.00 |
|
curved |
m |
12.00 |
|
Quadrants
305 mm * 305 mm * 150 mm |
Nr |
11.00 |
|
305 mm * 305 mm * 255 mm |
Nr |
12.00 |
|
457 mm * 457 mm * 150 mm |
Nr |
13.00 |
|
457 mm * 457 mm * 255 mm |
Nr |
14.00 |
|
Pavings
VegetabIe soiI SeIected from spoiI
heaps grading Prepared for turfing or seeding to generaI sursides
ave 75
mm thk |
m2 |
1.50 |
|
ave 100 mm thk |
m2 |
2.00 |
|
ave 125 mm thk |
m2 |
2.20 |
|
ave 150 mm thk |
m2 |
2.30 |
|
ave 175 mm thk |
m2 |
2.40 |
|
ave 200 mm thk |
m2 |
2.60 |
|
SeIected from spoiI heaps grading Prepared for
turfing or seeding to cuttings or embankments
ave 75 mm thk |
m2 |
2.00 |
|
ave 100 mm thk |
m2 |
2.30 |
|
ave 125 mm thk |
m2 |
2.40 |
|
ave 150 mm thk |
m2 |
2.60 |
|
ave 175 mm thk |
m2 |
2.70 |
|
ave 200 mm thk |
m2 |
2.80 |
|
Imported vegetabIe soiI Grading Prepared for
turfing or seeding to generaI sursides ave
75 mm thk |
m2 |
2.40 |
|
ave 100 mm thk |
m2 |
2.60 |
|
ave 125 thk |
m2 |
3.00 |
|
ave 150 mm thk |
m2 |
4.00 |
|
ave 175 mm thk |
m2 |
4.30 |
|
ave 200 mm thk |
m2 |
4.70 |
|
Grading Prep for turfing or seeding to cuttings or
embankments ave
75 mm thk |
m2 |
2.60 |
|
ave 100 mm thk |
m2 |
3.00 |
|
ave 125 mm thk |
m2 |
3.50 |
|
ave 150 mm thk |
m2 |
4.00 |
|
ave 175 mm thk |
m2 |
4.50 |
|
ave 200 mm thk |
m2 |
5.00 |
|
FertiIizer Prime Cost Sum £8 / 25 kg FertiIizer
0.08 kg per m raking in generaI sides |
m2 |
0.30 |
|
SeIected grass seed Prime Cost Sum £70 / 25kg
Grass seed sowing at a rate of 0.05 kg per m 2 appIications raking in
generaI
sides |
m2 |
0.75 |
|
cuttings or embankments |
m2 |
0.80 |
|
Preserved turf from stack on site Turfing
generaI
sides |
m2 |
1.50 |
|
cuttings or embankments shaIIow |
m2 |
1.75 |
|
cuttings or embankments steep pegged |
m2 |
2.25 |
|
Imported turf seIected meadow turf
Turfing generaI
sides |
m2 |
3.00 |
|
cuttings or embankments shaIIow |
m2 |
3.00 |
|
cuttings or embankments steep pegged |
m2 |
3.50 |