D20  BULK EXCAVATION AND FILLING RATES PER M2 M3 M

Get a quoted rate from a contractor listed on Bulk.Excavation@tradelocator.co.uk

   products and services to buy - press me

  for up to date prices buy our Live-up-date service

   where over 18,000 unit rates are up dated daily

 

D20  EXCAV AND FILLING - Earthwork support with Trench Boxes & Props n.e. 1m deep

  Bookmark and Share

.  
Supported face n.e. 1m apart with depth n.e. 0.5m m2               1.00
Supported face n.e. 2m apart with depth n.e. 0.5m m2               2.00
Supported face n.e. 4m apart with depth n.e. 0.5m m2               2.00
Supported face n.e. 1m apart with depth n.e. 1m m2               2.00
Supported face n.e. 2m apart with depth n.e.1m m2               2.00
Supported face n.e. 4m apart with depth n.e. 1m m2               2.00

D20  EXCAV AND FILLING - Earthwork support with Trench Boxes & Props n.e. 2-6m deep

.  
Supported face n.e. 1m apart with depth n.e. 2m m2               2.00
Supported face n.e. 2m apart with depth n.e. 2m m2               2.00
Supported face n.e. 4m apart with depth n.e. 2m m2               3.00
Supported face n.e. 1m apart with depth n.e. 4m m2               3.00
Supported face n.e. 2m apart with depth n.e. 4m m2               3.00
Supported face n.e. 4m apart with depth n.e. 4m m2               4.00
Supported face n.e. 1m apart with depth n.e. 6m m2               4.00
Supported face n.e. 2m apart with depth n.e. 6m m2               5.00
Supported face n.e. 4m apart with depth n.e. 6m m2               7.00
   
   
Earthwork support; next to roadways; left in with the measurement of space from the opposing faces of 1.00m to 2.00m; depth max. of n.e.     
6.00 m; m2             17.00
with the measurement of space from the opposing faces of 2.00m  to 4.00m; depth max. of n.e.    
1.00 m m2             18.00
2.00 m  m2             19.00
4.00 m; m2             20.00
6.00 m; m2             23.00

D20  EXCAV AND FILLING - SURFACE WORK

.  
Sloping surface trimming by hand m2               4.00
Sloping surface trimming by machine m2               1.00
Compacting Surfaces in General by machine m2               3.00
Compacting Surfaces in General using Compactor Plate Petrol 300mm(12in) m2               1.00
Compacting Surfaces in General using Compactor Plate Petrol 300mm (12in) m2               1.00
Compacting Surfaces in General using Compactor Plate Petrol 350mm (1in) m2               1.00
Compacting Surfaces in General using Compactor Plate Petrol 400mm (1in) m2               1.00
Compacting Surfaces in General using Forward / Reversible Compactor Plate Diesel 400mm (16in) m2               1.00
   
   
Compacting Surfaces in General using Forward / Reversible Plate Diesel 500mm (20in) m2               1.00
Compacting Surfaces in General using Compactor Plate Petrol 350mm (14in) Anti - Vibration m2               1.00
Compacting Surfaces in General using Compactor Plate Petrol 500mm (2in) m2               1.00
Compacting Surfaces in Pits by machine m2               5.00
Compacting Surfaces in Pits using Compactor Plate Petrol 300mm(12in) m2               3.00
Compacting Surfaces in Pits using Compactor Plate Petrol 300mm (12in) m2               3.00
Compacting Surfaces in Pits using Compactor Plate Petrol 350mm (1in) m2               2.00
Compacting Surfaces in Pits using Compactor Plate Petrol 400mm (1in) m2               2.00
Compacting Surfaces in Pits using Forward / Reversible Compactor Plate Diesel 400mm (16in) m2               3.00
Compacting Surfaces in Pits using Forward / Reversible Plate Diesel 500mm (20in) m2               3.00
Compacting Surfaces in Pits using Compactor Plate Petrol 350mm (14in) Anti - Vibration m2               2.00
Compacting Surfaces in Pits using Compactor Plate Petrol 500mm (2in) m2               2.00
Compacting Surfaces in Trenches by machine m2               4.00
Compacting Surfaces in Trenches using Compactor Plate Petrol 300mm(12in) m2               2.00
Compacting Surfaces in Trenches using Compactor Plate Petrol 300mm (12in) m2               2.00
Compacting Surfaces in Trenches using Compactor Plate Petrol 350mm (1in) m2               1.00
Compacting Surfaces in Trenches using Compactor Plate Petrol 400mm (1in) m2               1.00
Compacting Surfaces in Trenches using Forward / Reversible Compactor Plate Diesel 400mm (16in) m2               2.00
Compacting Surfaces in Trenches using Forward / Reversible Plate Diesel 500mm (20in) m2               2.00
Compacting Surfaces in Trenches using Compactor Plate Petrol 350mm (14in) Anti - Vibration m2               1.00
Compacting Surfaces in Trenches using Compactor Plate Petrol 500mm (2in) m2               1.00
D20  EXCAV AND FILLING  - Disposal - By Machine    
Excav disposal off site, inc LFT m3          155.00
Dry sand fine  disposal off site, inc LFT m3          128.00
Dry sand coarse  disposal off site, inc LFT m3          159.00
Topsoil (some moisture) disposal off site, inc LFT m3          143.00
Ballast disposal off site, inc LFT m3               7.00
   
   
Excav disposal on site, under 50m distance m3               7.00
Dry sand fine  disposal on site, under 50m distance m3               7.00
Dry sand coarse  disposal on site, under 50m distance m3               7.00
Topsoil (some moisture) disposal on site, under 50m distance m3               7.00
Ballast disposal on site, under 50m distance m3               7.00
Excav disposal on site, over 50m distance m3               9.00
Dry sand fine  disposal on site, over 50m distance m3               9.00
Dry sand coarse  disposal on site, over 50m distance m3               9.00
Topsoil (some moisture) disposal on site, over 50m distance m3               9.00
Ballast disposal on site, over 50m distance m3             10.00

D20  EXCAV AND FILLING - FILLING BY HAND/MACHINE

.  
Hardcore / MOT Type 1 / Type 1, by hand n.e. 300 deep m3             85.00
Hardcore / MOT Type 1 / Type 1, by hand ex. 300 deep m3             81.00
Hardcore / MOT Type 1 / Type 1, by machine n.e. 300 deep m3             83.00
Hardcore / MOT Type 1 / Type 1, by machine ex. 300 deep m3             81.00
Preserved topsoil obtained from on site spoil heaps not > 100 m travel - using a machine Making up levels by filling    
ave. thickness n.e. 0.25m  m3               7.00
Imported topsoil; n.e. 50 m - using a machine Making up levels by filling ave. thickness n.e. 0.25m  m3             21.00

Q05 EXCAV & FILLING - By Hand

.  
Topsoil for use elsewhere to a max. depth of 100mm m2               6.00
Topsoil for use elsewhere to a max. depth of 200mm m2               7.00
Topsoil for use elsewhere to a max. depth of 300mm m2             10.00
Topsoil for use elsewhere to a max. depth of 400mm m2             10.00
Topsoil for use elsewhere to a max. depth of 500mm m2             12.00
Reducing Levels to a max. depth of 100mm m3             24.00
Reducing Levels to a max. depth of 200mm m3             25.00
Reducing Levels to a max. depth of 300mm m3             26.00
Reducing Levels to a max. depth of 400mm m3             26.00
Reducing Levels to a max. depth of 500mm m3             27.00
   
   
Trenches ex. 300 grth to a max. depth of 100mm m3             28.00
Trenches ex. 300 grth to a max. depth of 200mm m3             29.00
Trenches ex. 300 grth to a max. depth of 300mm m3             29.00
Trenches ex. 300 grth to a max. depth of 400mm m3             30.00
Trenches ex. 300 grth to a max. depth of 500mm m3             31.00
Trenches ex. 300 grth to a max. depth of 600mm m3             32.00
Trenches ex. 300 grth to a max. depth of 700mm m3             33.00
Trenches ex. 300 grth to a max. depth of 800mm m3             34.00
Trenches ex. 300 grth to a max. depth of 900mm m3             34.00
Trenches ex. 300 grth to a max. depth of 1000mm m3             35.00
Pits ex. 300 grth to a max. depth of 500mm m3             35.00
Pits ex. 300 grth to a max. depth of 600mm m3             36.00
Pits ex. 300 grth to a max. depth of 700mm m3             36.00
Pits ex. 300 grth to a max. depth of 800mm m3             37.00
Pits ex. 300 grth to a max. depth of 900mm m3             38.00
Pits ex. 300 grth to a max. depth of 1000mm m3             38.00
E/O Bricks m3             89.00
E/O Rock m3          147.00
E/O Conc m3          111.00
Backfilling Working Space with Excav m3             40.00

Q05 EXCAV & FILLING - By Machine

.  
Topsoil for use elsewhere to a max. depth of 100mm m2               1.00
Topsoil for use elsewhere to a max. depth of 200mm m2               1.00
Topsoil for use elsewhere to a max. depth of 300mm m2               1.00
Topsoil for use elsewhere to a max. depth of 400mm m2               1.00
Topsoil for use elsewhere to a max. depth of 500mm m2               1.00
Reducing Levels to a max. depth of 250mm m3               5.00
Reducing Levels to a max. depth of 500mm m3               4.00
Reducing Levels to a max. depth of 750mm m3               4.00
Reducing Levels to a max. depth of 1000mm m3               3.00
Reducing Levels to a max. depth of 1250mm m3               3.00
Trenches ex. 300 grth to a max. depth of 250mm m3             18.00
Trenches ex. 300 grth to a max. depth of 500mm m3             18.00
Trenches ex. 300 grth to a max. depth of 600mm m3             17.00
Trenches ex. 300 grth to a max. depth of 700mm m3             17.00
Trenches ex. 300 grth to a max. depth of 800mm m3             16.00
Trenches ex. 300 grth to a max. depth of 900mm m3             16.00
Trenches ex. 300 grth to a max. depth of 1000mm m3             16.00
Trenches ex. 300 grth to a max. depth of 1100mm m3             15.00
Trenches ex. 300 grth to a max. depth of 1200mm m3             15.00
Trenches ex. 300 grth to a max. depth of 1300mm m3             15.00
   
   
Pits ex. 300 grth to a max. depth of 500mm m3             25.00
Pits ex. 300 grth to a max. depth of 600mm m3             23.00
Pits ex. 300 grth to a max. depth of 700mm m3             22.00
Pits ex. 300 grth to a max. depth of 800mm m3             21.00
Pits ex. 300 grth to a max. depth of 900mm m3             20.00
Pits ex. 300 grth to a max. depth of 1000mm m3             20.00
E/O Bricks m3             70.00
E/O Rock m3          151.00
E/O Conc m3          101.00
Backfilling Working Space with Excav m3             21.00

Do you want more insight on rates more control more relevance more productivity then have a look at at what the Dynamic Schedule of Rates for Measurement (NSRM) offers you

For upto date rates buy our Dynamic service with over 18,000 unit rates in 244 work sections with Dataflow

 

Schedule of Rates - Dynamic (it's just 20p per day)
buy your dynamic access to 12 month of construction rates schedule of rates for the very small price of 73.00
Construction Software
Manufactured by: Construction Rates
Model: Dynamic Schedule of Rates UK
Product ID: Dataflow Version 001.2016.10
 
73.00 New
 

Building Construction Schedule of Rates UK - Dynamic

 

These are tools for construction professionals. You must double check the correctness of all rates and quantities before tendering and or entering into a contract with another party. All rates and prices generated are provided as a general indication only and may differ depending upon site conditions, volume etc. We do not warrant their accuracy. Remember, the correct rates are the ones with which a quality specialist is prepared to enter into contract with you.  ALL quantities should be checked and double checked. We do not warrant the suitability of any organisation contained within this site. The producers of this site will accept no liability whatsoever for any loss [howsoever arising] which may result from using this or any information on or obtained from this site. You must accept the above before you may use this site. You are responsible for any losses that may result from not checking all rates with an appropriate source. If you Do Not Accept the above you should not use any information in any way. (c) Copyright Construction Rates 2001 - By continuing you are accepting our copyright and our conditions.

 

 

   products and services to buy - press me

 

  http://www.constructionrates.co.uk/

 

             

  [ If you have problems downloading with this e-mail, make sure you are on-line and that your security settings are not too high,

  [see menu bar] Select Tools, Option, Security and make sure you're set on the Internet Zone. ]

    

 

 Trade Locator

   

     Helping you  to find trade contractors fast - Another service from  www . construction rates . co . uk

    

| prices | rates | supply chain directory| specification| products | supply & fix rates

 Construction is our world

 Construction is your world

 Get your message across in our world

 

    

      email us now

 

| play the Daywork Game price data at the speed of light |